P-1889

Archived Posts from this Category

Connecticut River shortnose sturgeon: a spectacular failure to protect

Posted by on 26 Mar 2020 | Tagged as: Christopher Chaney, Christopher Cheney, Clean Water Act, Connecticut River, Connecticut River pollution, Connecticut River riverbank failure, Connecticut River shortnose sturgeon, Dr. Boyd Kynard, Endangered Species Act, EnviroSho, Federal Energy Regulatory Commission, federally-endangered shortnose sturgeon, FERC, FirstLight, FirstLight Power Resources, Kimberly D. Bose, MA Division of Fish and Wildlife, manganese pollution, Massachusetts Division of Fish & Wildlife, National Marine Fisheries Service, NMFS, P-1889, Rock Dam, Secretary Kimberly Bose, Turners Falls, Turners Falls power canal, Uncategorized, US Fish & Wildlife Service, www.whmp.com

Connecticut River shortnose sturgeon: a spectacular failure to protect
Copyright © 2020, by Karl Meyer. All rights reserved.

Photo Copyright © 2020, by Karl Meyer (click X3 to enlarge)
Well over 4 months since I registered my October 9, 2019 Comments describing critical erosion and polluting impacts on the Connecticut River at fragile habitat at the Rock Dam in Turners Falls–the sole documented natural spawning site for the federally endangered shortnose sturgeon in this river FirstLight Power Resources received instructions from the Federal Energy Regulatory Commission’s Christopher Cheney at the Office of Hydro Compliance. On February 21, 2020, they included the following:

“Dear Mr. Traester:

On October 9, 2019, we received a complaint regarding erosion in the bypassed reach of the Turners Falls Project No. 1889. According to the complaint, releases from the dam caused erosion in the area known as the Rock Dam in the project’s bypassedreach. For us to complete our review of the of the complaint, please file the followinginformation within 30 days of the date of this letter:

1. Photographs and the location(s) and an estimate of the extent(s) (e.g., height, width, depth) of the erosion in the bypassed reach identified in the October 9, 2019complaint.”

Here are some key points, verbatim, from my October 9, 2019 letter, including impacts on this fragile endangered-species spawning site and habitat—and addressing as well, federal and state laws and license conditions:

“In recent weeks I have noted increasingly steady water leakage in the riverbanks above the Rock Dam site, leading to constant water flow intrusions along these banks. Less than 400 feet away sits the downstream, outer-right banking curve of the Turners Falls power canal, which is the apparent source of these increasing water intrusions.
Photo Copyright © 2020, by Karl Meyer.

In a visit to the Rock Dam site on October 8, 2019, I noted the dramatic collapses of a long section of riverbank adjacent to the Rock Dam. This collapse, of some 25 feet in width and dropping down between 5 – 10 feet toward the river, is apparent in my attached photo. Please note that the draped yellow jacket in the foreground is approximately 3-1/2 feet across. This new bank collapse is just south, by perhaps 30 feet, from an earlier recent collapse of a smaller scale of some 6 feet across, occurring at approximately the same bank level. At both of these sites there has been a serious leaching of manganese, the red colored flow toward the river and the sand and cobbles that constitute the shortnose sturgeon spawning site and egg/embryo nursery unique to this reach. Photo Copyright © 2020, by Karl Meyer. (click X3 to enlarge)

Please take action requiring immediate remedy to this situation, which appears to concern license and statute infractions that run afoul of the federal Endangered Species Act, the Clean Water Act, and Article 17 concerning erosion; Article 19, concerning construction and maintenance; Article 18 concerning fishing access; and Article 35 concerning State Historic Preservation under the current license for P-1889.”
Photo Copyright © 2020, by Karl Meyer (click x3 to enlarge)

FirstLight responded on March 20, 2020. They included an all-but-useless satellite shot for a federal agency that has exact information on this site, and pictures of boulder-rubble that connect directly to their dumped rubble that is currently tumbling from their ancient attempts to shore up the failing Connecticut River banks above and adjacent to the TF power canal.
This is evidence of the power company’s failure in decades past. They now attempt infer that the tumbled rocks here are the work of the public and fishermen, not the failed detritus of their ongoing neglect.

FirstLight also failed to address the requested measurements from FERC. And, as to my original complaint, they leave out any mention of manganese, the intrusions and water—and it’s leaching and crumbling connections to the Turners Falls power canal; as well as failure to protect and maintain critical shortnose sturgeon spawning habitat. Nor does FL address the ESA, Clean Water Act, and current FERC license conditions required at this site. Below are excerpts from FL’s response, and below that is a link that you may be able to use to access FirstLight’s full response to FERC:

“FirstLight cannot provide dimensions of the extent of the erosion because there is no evidence of any recent erosion in this natural river channel.”
Above photo taken March 25, 2020 w/sturgeon expert Dr. Boyd Kynard at right, on the failed banks adjacent to Rock Dam. (click X3 to enlarge) Photo Copyright © 2020, by Karl Meyer.

Further, FL states, “Photographs were taken on October 29, 2019, after the October 9, 2019 complaint letter. Note moss on the rocks located within the side channel in Photos Nos. 1 and 2, indicating the preexistenceof a wet environment. Note also a Photo No. 3 showing ~12” rocks placed across the side channel. This section of the bypass reach is frequented by the public in summer months. The rocks aligned across the side channel appear to have been placed by unknown members of the general public, possibly to form a barrier or walk path across the side channel, suggesting that the channel is frequently wetted.”

You may be able to access FirstLight’s full response to FERC by copying an pasting the link below:https://elibrary.ferc.gov/idmws/file_list.asp?accession_num=20200318-5043

You may also want to Comment directly to the Federal Energy Regulatory Commission.
Here’s how:
Go to www.ferc.gov ; then to file E-Comment; from there to Documents and Filings; then to Hydro; then to Washington DC; then paste-in P-1889 for the Project # (you must have this), then check the little X Box; then address your comments to “Secretary Kimberly D. Bose” and comment away! Make sure to include your own contact information.

AND, from FERC Hydro Compliance: Christopher.Chaney@ferc.gov

Also, you may want to contact your agency representatives negotiating on the public’s behalf in the current FERC relicensing. They will assuredly forward your message to their Department Chiefs who are responsible for the CURRENT license and river conditions and enforcement:

For the National Marine Fisheries Service: julie.crocker@noaa.gov
For US Fish & Wildlife Service: ken_sprankle@fws.gov ; melissa_grader@fws.gov
For MA Div. of Fish & Wildlife: caleb.slater@state.ma.us

There’s also your federal and state/local reps: Warren, McGovern, Comerford, etc., all represent you! And, you can write to the local media—this effects all at the ground level, and into the future.

Also, a few recent radio spots addressing this issue, below, with thanks to Bob, d.o., and Glen!

The Enviro Show

The Shortnose Sturgeon are Coming to Spawn –in THIS?

Intervening for the Connecticut River Ecosystem

Posted by on 13 Nov 2019 | Tagged as: Connecticut River ecosystem, Connecticut River shortnose sturgeon, Douglas Bennett, Dr. Boyd Kynard, Endangere Species Act, ESA, Federal Conte Anadromous Fish Research Center, Federal Energy Regulatory Commission, Federal Recovery Plan, federally-endangered Connecticut River shortnose sturgeion, FirstLight Power Resources, Kleinschmidt Associates, Micah Kieffer, National Marine Fisheries Service, National Marine Fisheries Service, NMFS, Northfield Control Room, Northfield Mountain Pumped Storage Project, P-1889, P-2485, Recovery Plan for the Shortnose Sturgeon (Acipenser brevirostrum), Rock Dam, Secretary, Section 9–Prohibition of Take Section 9(a)(1), Steven Leach, Turners Falls dam, Uncategorized, US Fish & Wildlife Service, US Fish and Wildlife Coordination Act

NOTE: below, find photographic evidence and the text of my Request for Rehearing delivered to Federal Energy Regulatory Commission Secretary Kimberly D. Bose on August 11, 2019. My request was granted. I will update this posting when FERC delivers its decision on whether FirstLight can be approved for several Transfer of License applications while being out of compliance with current license requirements that have impacted the critical habitat and spawning of a federally-endangered migratory fish. Text begins below photos.

ALSO here: https://www.youtube.com/watch?v=WZVyFgoFYyA is a link to Episode 187 of Local Bias that I recorded with host Drew Hutchison at the studios of Greenfield Community Television. It is running throughout November on GCTV, and has been broadcast in Hadley, MA, HQ home of Region 5, US Fish & Wildlife Service.


PHOTO: dewatered shortnose sturgeon spawning pool at the Rock Dam in the early hours of May 17, 2019. (Click x3 to enlarge)
Photo Copyright © 2019 by Karl Meyer All rights reserved.


PHOTO: Closed bascule gates and cut-off flow to the main stem Connecticut River on the morning of May 17, 2019. (Click x3 to enlarge)
Photo Copyright © 2019 by Karl Meyer All rights reserved.

Karl Meyer, M.S. Environmental Science
91 Smith Street
Greenfield, MA, 01301
karlmeyer1809@verizon.net

August 11, 2019

The Honorable Kimberly D. Bose, Secretary
Federal Energy Regulatory Commission
88 First Street, NE
Washington, DC 20426

Request for a Rehearing of Commission’s July 11, 2019 Order Approving Transfer of License and Substitution of Relicensing Applicant for P-2485-077, FirstLight Hydro Generating Company to Northfield Mountain LLC; and P-1889-088, FirstLight Hydro Generating Company to FirstLightMA Hydro LLC.

Specifically: the FirstLight Hydro Generating Company, Project No. 2485-077 Northfield Mountain LLC) APPLICATION FOR APPROVAL OF TRANSFER OF LICENSE, SUBSTITUTION OF APPLICANT, AND REQUEST FOR EXPEDITED CONSIDERATION; and FirstLight Hydro Generating Company, Project No. 1889-088, FirstLight MA Hydro LLC ) APPLICATION FOR APPROVAL OF TRANSFER OF LICENSE, SUBSTITUTION OF APPLICANT, AND REQUEST FOR EXPEDITED CONSIDERATION

Dear Secretary Bose,

I request that the Commission rehear and review its expedited decision regarding P-2485 and P-1889. This request is being made in part because I believe the Commission erred when it stated in its approvals of the transfers under the Section D headings that “The Transferer is in Compliance with the License.”

FERC’s decision that FirstLight, in its Section 12 Discussion statements, “demonstrated this transfer is in the public Interest,” was made in error—particularly with respect to its Section 16 statements that, “Our review of the compliance history of the project shows that the licensee has been in compliance.” And further, in FERC’s Section 17 Discussion statements that, “In conclusion, we find that Northfield’s transfer application demonstrates that it is qualified to be the licensee for the project. In this case, the transferee has provided documentation showing its fitness to comply with the terms and conditions of the license.”

My request for a rehearing and withdrawal of the Commission’s July 11, 2019 decision granting these license transfers is that FirstLight was not in compliance of the terms and conditions of its license on May 17, 2019 respecting the federal Endangered Species Act, Section 9.(ESA section 9 makes it unlawful to take (harass, harm, kill, etc.) any endangered species.), as well as Article 45: “The operating of Project No. 2485 shall be coordinated with the operation of Project No. 1889.”

Section 9–Prohibition of Take Section 9(a)(1) makes it illegal to take²² an endangered species of fish or wildlife. The take prohibition has been applied to most threatened species by regulation. ²² *: Take–to harass, harm, pursue, hunt, shoot, wound, kill, trap, capture, or collect, or attempt to engage in any such conduct (section 3 of the ESA–definitions). Harm means an act that actually kills or injures wildlife, and may include significant habitat modification or degradation where it actually kills or injures wildlife by significantly impairing essential behavioral patterns, including breeding, feeding, or sheltering (50 CFR § 17.3, § 222.102).

On May 9, 2019, US Geological Services Micah Kieffer, Research Fishery Biologist at the LSC Conte Anadromous Fish Laboratory detected a signal from a radio-tagged shortnose sturgeon at the Rock Dam, a documented natural SNS spawning site on the Connecticut River. Kieffer, a sturgeon specialist, set two nets in the river overnight, and returned early on the morning of May 10, 2019, to find 48 federally endangered shortnose sturgeon in those nets.

In turn, on May 13, 2019, Kieffer emailed a report of this finding in his ongoing work to biologists and various interested parties and SNS stakeholders, noting: “This past Thursday evening we dropped two gill-nets in the Rock Dam pool. Expecting to capture only a few fish, on Friday morning we instead landed 48 individuals: four females (two pre-spawning, one running, one spent) and 44 males (all running sperm) (pers. comm.)” Duly apprised of the presence and apparent spawning activity of that federal endangered species were two biologists working for FirstLight Power Resources–Steven Leach, Senior Fishery Biologist, FirstLight Power Resources, Inc., and Chris Tomichek, Senior Manager, Kleinschmidt Associates, working as a FL consultant.

In an updating May 22, 2019 email that again included fishery and agency biologists and stakeholders, including myself and FL’s Steven Leach and Chris Tomichek, Kieffer noted:

“Greetings to all SNS stakeholders:
Here is an update on the monitoring of SNS spawning at Montague for 2019. Following the May 13 report, we set additional nets on three days (May 14, 16, and 17), mostly at Rock Dam, but a few at Cabot and the Deerfield River, all day-sets to avoid excessive captures like that we experienced on 5/10. These efforts resulted in the additional capture of 11 fish on 5/14 and another 11 on 5/16 (we got skunked on the 17th). Within these efforts, we captured an additional female running eggs that received an external tag, and we also internally tagged three males, two that we PIT-tagged 25 years ago!”

Having been apprised of SNS spawning activity having been observed at Rock Dam on May 10, 2019, I found the Rock Dam spawning and rearing site had had its flows cut and its banks dewatered just a week later, on the morning of Friday, May 17, 2019. That is the same morning when Kieffer later recorded getting “skunked” at Rock Dam. Upstream, FL had shut bascule gates 2, 3, and 4, while pinching down Bascule 1 to just a few hundred CFS. See photos attached. Flow at the Rock Dam had been ramped down to a shallow lick of whitewater, while robust flows have been documented as necessities for females to remain on that spawning ground. Further, the cobble banks had been dewatered, habitat where embryos shelter and develop. The practice is lethal.

In short, FL’s actions at the dam, controlled from upstream at the Northfield Mountain Pumped Storage Station, directly interfered and imperiled SNS spawning. They did this at a time when they were apprised of SNS presence and should have executed the utmost diligence—FL, of its own volition, was in the process of implementing its own test flows for the By Pass reach.

The presence and spawning activity requirements of shortnose sturgeon in the project areas–and within the influences of P-1889 and P-2485 has been known by the license holders for decades. Indeed, several studies were referenced in the PAD, before the beginning of the current relicensing:

From the Northfield Mountain/Turners Falls Pre-Application Document, October 2012, Section 6:

LITERATURE AND INFORMATION SOURCES CITED IN THE DESCRIPTIONS AND SUMMARIES OF EXISTING RESOURCE DATA (18 C.F.R. § 5.6 (c)(2)), pp. 297. – 301
Fish and Aquatic Resources, Sections 6-3, 6-4, 6-5.

Kieffer, Micah & Boyd Kynard. (2007). Effects of Water Manipulations by Turners Falls Dam Hydroelectric Complex Rearing Conditions for Connecticut River Shortnose Sturgeon Early Life Stages. S.O. Turners Falls. MA: Conte Anadromous Fish Research Center.

National Marine Fisheries Service (NMFS). (1998). Recovery Plan for the Shortnose Sturgeon (Acipenser brevirostrum). Prepared by the Shortnose Sturgeon Recovery Team for the National Marine Fisheries Service, Silver Spring, Maryland. 104 pages.

In an email to SNS stakeholders from FirstLight Manager Douglas Bennett, responding to an inquiry from US Fish & Wildlife Biologist Melissa Grader about see-sawing flows and bascule gate settings, Bennett noted that the FL settings impacting SNS spawning and habitat in the By Pass at Rock Dam in the P-1889 Project area had been implemented in the control room of NMPS, P-2485:

“On Friday morning at approximate 1000 the flows receded enough so that the 6500 cfs by-pass flows were initiated by discharging 4400 cfs over Bascules 1 and 4 and 2100 cfs at TF #1 Station.

The 6500 cfs by-pass flows were maintained until 2400 on Saturday evening when by-pass flows were dropped to 4400 cfs, discharging 2400over Bascule gate 1 and 2100 at TF #1 Station. This was an error on our part due to misinterpretation of conflicting schedules in the Northfield Control Room. Corrective actions have been taken to prevent this going forward.”

I witnessed the Rock Dam water-starved and bank-exposed at 5:30 a.m., and my photo of the listless spill with ONLY Bascule 1 open, was taken at 7:30 a.m. Mr. Bennett’s note states that flows had not come down enough to implement FL-initiated test flows until 1000 hrs. He did not mention the setting hours earlier that I documented. Thus, apparently, there had been a ramping down of the bascule from within the NMPS control room sometime in the early morning hours, with the result of further impacts on spawning SNS through a jumble of see-sawing gate settings.

The Commission notes in its granting of these Transfers that “Section 8 of the FPA requires “any successor or assign of the rights of such licensee . . . shall be subject to all the conditions of the license under which such rights are held by such licensee and also subject to all the provisions and conditions of [the FPA] to the same extent as though such successor as assign were the original licensee.”24. FirstLight, at a time when it was apprised of the presence of a federally endangered species did not meet its license requirements here—regarding the ESA Section 9, and the only federally-endangered migratory fish in the Connecticut River

The Commission further stated that, “Northfield is affiliated with companies in the operation and maintenance of hydroelectric projects and will have access to their expertise.” Their actions clearly demonstrate there was no expertise shown or relayed between P-2485 and P-1889 at this critical time.

The Commission noted, in their decision: “In conclusion, we find that Northfield’s transfer application demonstrates that it is qualified to be the licensee for the project. In this case, the transferee has provided documentation showing its fitness to comply with the terms and conditions of the license.”

Their actions clearly call the company’s fitness to operate these plants into question. Is FERC’s finding that these transfers are “in the public’s interest” valid? FL clearly did not coordinate operations between P-2485 and P-1889 at this critical time, which is clearly spelled out in Article 45 of their license. Those actions should have been updated with the Commission and investigated before a Transfer finding was granted. An investigation and exploration of impacts and penalties under Section 9 of the ESA should be undertaken by the Commission before these transfers are validated.

I therefore request that the Commission undertake a rehearing of these license transfers. The grantor and grantee need to demonstrate they can comply with federal regulations to operate these facilities. Please see attachments.

Thank you for your careful review of these matters.

Sincerely,