Stakeholder PROTEST of FERC Revised Study Plan finding endangering Connecticut River shortnose sturgeon

Posted by on 07 Mar 2016 | Tagged as: Connecticut River shortnose sturgeon, Dead Reach, Dr. Boyd Kynard, endangerd shortnose sturgeon, Endangered Species Act, ESA, Extinction, Federal Energy Regulatory Commission, federally-endangered shortnose sturgeon, FERC, Fish and Aquatics Study Team, GDF-Suez FirstLight, MA Division of Fish and Wildlife, National Marine Fisheries Service, NMFS, NOAA, Rock Dam, Secretary Kimberly Bose, US Fish & Wildlife Service, USFWS

(The following Stakeholder testimony was submitted to FERC on March 4, 2016)

Karl Meyer, M.S.
85 School Street # 3
Greenfield, MA, 01301
413-773-0006 March 4, 2016

The Honorable Kimberly D. Bose, Secretary
Federal Energy Regulatory Commission
88 First Street, NE
Washington, DC 20426

RE: P-1889 and P-2485, and federally-endangered Connecticut River shortnose sturgeon, (Acipenser brevirostrum)

PROTEST of FERC-sanctioned Revised Plan for Study 3.3.19, issued to FirstLight Power Resources, Inc, in a February 25, 2016 FERC letter to Mr. James P. Donohue of FirstLight, by Vince E. Yearick, FERC Director, Division of Hydropower Relicensing.

Dear Secretary Bose,

I protest the FERC finding issued on February 25, 2016 for P-2485 and P-1889 specifically because it sanctions test flows that are documented to cause spawning failure for the federally-endangered Connecticut River shortnose sturgeon (Acipenser brevirostrum) at its only documented natural spawning site, the Rock Dam, in the Connecticut River. FirstLight has proposed and FERC has accepted Study Plan test flows of 1500 cubic feet per second in the CT River’s By Pass Reach for April, May and June 2016. That low level of flow will displace and wipe out a full season’s spawning and rearing of Young of Year life stage SNS at their ancient Rock Dam nursery site.

Though my FERC Stakeholder comments of January 28, 2016 specifically addressed this ESA issue, FirstLight did not respond to the endangerment issue in its RSP revisions. Further, I had made this issue clear to FirstLight and its agents, FERC staff, and key stakeholder agencies in an email delivered on January 20, 2016. I again reiterated the endangered species impacts to those same parties in an email delivered on February 24, 2016. Madam Secretary, I again made my concerns about spawning interference and failure to you and for the FERC record in a letter delivered February 26, 2016. All are available for perusal in the FERC record for P-2485 and P-1889.

Shortnose sturgeon gather at this spawning and nursery site annually between April 22 and May 25 for pre-spawning and spawning. Further, the complex of key biological characteristics of flow, varying depths, and cobble/sand habitat provide SNS with protective options that nurture developing Young of the Year throughout June into July.

According to 17 years of published studies at that site documented by Dr. Boyd Kynard and research colleagues, a continuous minimum flow of 2500 cfs is required to protect sturgeon spawning and rearing at this site. Therefore, I PROTEST the findings of the FERC Revised Study Plan determination issued by FERC on February 25, 2016, and request that only continuous protective minimum flows of 2500 cfs be allowed in this study, and throughout the 2016 SNS spawning and rearing season, as well as all ensuing springs.

The following publication has been referenced in the FERC ILP for these projects by both federal and state stakeholder agencies, FERC, as well as FirstLight and their agents.

“LIFE HISTORY AND BEHAVIOUR OF CONNECTICUT RIVER SHORTNOSE AND OTHER STURGEONS, 2012, by Boyd Kynard, Paolo Bronzi et al, World Sturgeon Conservation Society: Special Publication # 4

“Effect of hydroelectric operations on spawning”

Page 101, bottom: “During the 11 yr spawning failed (excluding the failed migration in 2002), when discharge levels were too low for 5 yr and too high for 4 yr. During one yr (2007), discharge during April was both to low and too high. When spawning failed at RockD due to low discharge during 4 yr (1995, 1998, 1999, and 2006)m discharge decreased to <70 m3 s-1 for at least 4 d by 30 April (Fig. 14), the earlier period of low discharge likely marked a threshold making the RockD unattractive to spawning fish.”

Further published data, tables, and required flows necessary in this reach appear on pages 101-102 of LIFE HISTORY AND BEHAVIOUR OF CONNECTICUT RIVER SHORTNOSE AND OTHER STURGEIONS.

I would welcome a FERC hearing on this critical ESA issue and would make myself available for testimony. Thank you for your attention to this pressing matter.

Sincerely,
Karl Meyer
Fish and Aquatics Study Team, P-2485 and P-1889

Cc’d via email to:
Brandon Cherry, FERC
James Donohue, FirstLight
Julie Crocker, NOAA
John Warner, USFWS
Caleb Slater, MA Division of Fisheries & Wildlife

FERC Stakeholder comments: Turner Falls Canal ultrasound study

Posted by on 06 Feb 2016 | Tagged as: American shad, Cabot Station, Connecticut River shortnose sturgeon, Dr. Boyd Kynard, endangerd shortnose sturgeon, Federal Energy Regulatory Commission, federally-endangered shortnose sturgeon, FERC, FirstLight, Fish and Aquatics Study Team, GDF-Suez FirstLight, Northfield Mountain Pumped Storage Station, Relicensing, Revised Study Plan, Rock Dam, Rock Dam Pool, Secretary Kimberly Bose, shad, Station 1, Turners Falls, Turners Falls dam, Turners Falls power canal

Karl Meyer, M.S.
85 School Street # 3
Greenfield, MA, 01301
January 28, 2016

The Honorable Kimberly D. Bose, Secretary
Federal Energy Regulatory Commission
88 First Street, NE
Washington, DC 20426

RE: P-1889 and P-2485, ILP for Turners Falls/Cabot Station and the Northfield Mountain Pumped Storage Project

Dear Secretary Bose,

The following comments pertain to an RSP and failures on the part of FirstLight Hydro Generating Company in following FERC’s SDL on Study 3.3.19 and Study 3.3.2. They were shared with FirstLight’s team and FERC’s Brandon Cherry on January 20, 2016:

As one of the requesters for an ultrasound study at Cabot Station, here are my comments, suggestions and observations for ways to gain the best applicable results from Study 3.3.19-Evaluate the Use of an Ultrasound Array to Facilitate Upstream Movement to Turners Falls Dam by Avoiding Cabot Station Tailrace.

Unfortunately, FirstLight has not provided Stakeholders with any preliminary findings from the telemetry data gathered in Study 3.3.2, which would be a great help in addressing any changes or improvements needed for a successful 3.3.19 Ultrasound Study.

As stated in their Study Determination Letter under Discussion and Staff Recommendations, FERC was very clear that 3.3.2 information on: (1) “delay,” (2) “bypass flows,” and (3) “effects of Station 1 operations on upstream shad migrations,” be brought over and included in the design recommendations for 3.3.19:

“These evaluation data can be used to inform the methods and design of this study (e.g., ultrasound array design, layout, and placement; array testing at appropriate bypass flows) (section 5.9(b)(6)).”

FERC further stated in their SD Letter to FirstLight, “The amended study 3.3.19 should address stakeholder comments and recommendations. If FirstLight does not adopt a recommendation, FirstLight should provide its reasoning based on project-specific circumstances (e.g. Study 3.3.2 results).”

Revised Study Plan 3.3.19 ignores FERC’s guidance on the inclusion and application of “bypass flows” and “effects of Station 1 operations on upstream shad migrations” in its design. Neither key issue is addressed in their proposal. Bypass flows, which are key to any application of acoustic guidance to keep shad moving upstream in the Bypass, are not included at all. Stakeholders originally requested this Study be done for two years, with bypass flows tested throughout.

Further, the only mention of Station 1 is in a footnote, without any reference to testing its effects “on upstream shad migration operations.” FirstLight merely notes that hourly data on discharges at that site will be included—with no insight on how that data would be applicable if fish are not monitored for migratory delay, with and without flows, emanating from that site.

Since the thrust of the Study is aimed at getting fish up through the Bypass, I question why just three monitoring sites are suggested to be deployed upstream of Cabot Station itself.

• Sonic guidance at Cabot should be deployed in such a way that it encourages upstream movement as much as possible—and avoids biasing fish movements toward downstream retreat. It should also be deployed in a way that, when in ON mode, it also ensonnifies the entrance to Cabot Ladder, as the thrust of the study is to have fish avoid the power canal.

• Ensonification should NOT be engaged in two hour increments, as this would likely be a source of stress and disorientation for fish. Employ the tests in 24 hour cyles, one full day on, one full day off.

• Data should also be provided on the hourly operation and number of gates open at the Emergency Spill Gates off the Canal at Cabot.

• I’d suggest removing the monitor upstream of the mouth of the Deerfield and placing it at the Rock Dam pool, a site where shad–and anglers have a historic presence in the Bypass. The agencies, as well as the anglers, are concerned with finding out where fish gather and stall in this reach on their way northern MA, VT, and NH.

• Another monitor needs to be placed at Station 1, another known fishing site. I interviewed a fisherman there last year with Station 1 running. There were scores of fish visible, treading water in the outflow. He flatly said there are “always shad here” when Station 1 is generating.

• Station 1 should be monitored and switched On and Off in tandem with the Cabot ensonification to highlight impacts, false attraction, drop-backs to Rock Dam and elsewhere, and delays.

• Flow data, hours and number of units in operation, and any interruptions in flow at Station 1 should be included in the Study.

• Several more monitors need to be deployed at the Dam and the Spillway entrance to capture the early, freshet aggregation of fish there—as this is what’s at the core of this study.

• Given that this study will only have one sampling season, it is vitally important that it has enough reach to be applicable for informing a hydro-relicensing that may remain in place for two decades. One month testing and data collection is needed at minimum.

• Further, given the “drop out” rate for handled fish, the number of tagged fish included from FirstLight’s consultants should be doubled to 200, in order to have an acceptable sample entering the project reach.

• Test flows from May 15th through mid-June: two weeks at 5,000 CFS; third week at 4,000 CFS. The final week should be at a minimum of 2,500 CFS—which, as FL has indicated in their response to a new Stakeholder Study suggested at the Rock Dam for shortnose sturgeon spawning: 2,500 CFS is the absolute minimum, uninterrupted flow necessary through the Bypass from April 25 – May 22, in order to not interfere with the spawning of a federally endangered species and be subject to court action. In their response, FL cited “Kynard” et al. Minimum flows to keep SNS embryos and eggs motile, watered, and viable are required throughout the month of June.

Thank you,
Karl Meyer, Fish & Aquatics Study Team

New comments to the Federal Energy Regulatory Commission

Posted by on 16 Nov 2015 | Tagged as: 5-year FERC licensing process, American shad, canal shad, Connecticut River, Connecticut River shortnose sturgeon, Dr. Boyd Kynard, Extinction, Federal Energy Regulatory Commission, federal trust fish, federally-endangered shortnose sturgeon, FERC, FERC license, FERC licensing process, FirstLight, GDF-Suez FirstLight, migratory delay, power canal studies, Public Comment period, Relicensing, Revised Study Plan, Rock Dam, Rock Dam Pool, shad, shad fishing, shortnose sturgeon, Station 1, Turners Falls, Turners Falls dam, Turners Falls power canal, Vermont

The following comments were submitted to the Federal Energy Regulatory Commission on November 13, 2015, respecting relicensing studies occurring at the Northfield Mountain Pumped Storage Station and at the Turners Falls Dam and Canal. They are designated, respectively as: P-2485; and P-1889.

Karl Meyer, M.S. Environmental Science
85 School Street # 3
Greenfield, MA, 01301
413-773-0006 November 13, 2014

The Honorable Kimberly D. Bose, Secretary
Federal Energy Regulatory Commission
88 First Street, NE
Washington, DC 20426

ILP COMMENTS on Updated Study Reports—including Disagreements/Modifications to Study/Propose New Study on Turners Falls Hydroelectric Project P- 1889, and Northfield Mountain Pumped Storage Project P-2485.

Dear Secretary Bose,

The Turners Falls Hydroelectric Project, P-1889, and the Northfield Mountain Pumped Storage Project, P-2485, are currently undergoing studies through the 5-year FERC relicensing process. The majority of the fish and aquatics studies remain incomplete at this time. However, having attended the recent study update meetings with FirstLight’s consultants, and as a member of the Fish & Aquatics Studies Team for P-2485 and P-1889, please accept these brief comments on the USR and proposals for modifications and new studies needed in the FERC ILP for these projects. As studies are brought to completion and data and results are shared with Stakeholders I will submit further comments.

3.3.2 Evaluate Upstream and Downstream Passage of American Shad

Needed information from this study: from personal observations I noted many days when Station 1 was in operation. I visited the site, took some photos, and interviewed a fisherman who was busy catching shad at the Station 1 Outflow on 5/24/2015. In good light, and without the advantage of polarizing sunglasses, I observed dozens of shad stacked up like cordwood, treading water there. The gentlemen noted that whenever Station 1 is running “there are always fish here.” The report should include information about tagged fish delayed in this false attraction water. It is also critical to delineate the number of days during testing that Station 1 was in operation.

3.3.6 Impact of Project Operations on Shad Spawning, Spawning Habitat and Egg Deposition in the Area of the Northfield Mountain and Turners Falls Projects.

In their update the applicant’s team stated that “because minimal shad spawning was observed in the Turners Falls Canal, no spawning areas in the canal were identified for further examination.”

Needed information from this study: at what hour, on what dates, and under what conditions were these “minimal” spawning observations made? Did they return to the site again under different, or more favorable conditions? What was the water temperature? Was it raining? Windy? Cloudy? Was Cabot Station running at the time-and how many units? Was Station 1 in operation on the nights they made their observations?

These are basic questions that require adequate answers as the TF Canal has been the bottleneck for the shad run up through Northern Massachusetts and into Vermont and New Hampshire these last 40 years. The canal appears to be culling off part of the run as a spawning trap. A thorough understanding of why fish are lingering there, and clear assessment of the numbers and delays of fish attempting to spawn in the canal is necessary for informed decision making.

3.3.18 Impacts of the Turners Falls Canal Drawdown on Fish Migration and Aquatic Organisms.

Needed information from this study: This study needs to be extended for another year. On October 5, 2015, I took a 20-minute walk through a small segment of the canal at 7:00 a.m. on the morning the canal had drained. On the flats far–from the thalweg where most of the 2014 assessment appears to have taken place, thousands of fish lay struggling, stranded, and dead in the drying pools. These included juvenile American shad, yellow perch, juvenile and “transformer” sea lamprey, one 8-inch chain pickerel, one crayfish, and thousands of tiny, unidentified YOY fish in drying pools and rills that led to nowhere.

These observations were made crossing just a few—out of the many acres, of silt and muck “shoulder habitat” that occurs away from the main channel on both the east and west sides of the TF Canal. A more thorough mortality assessment needs to be made across these habitats to have a full understanding of the impacts of the canal drawdown migrating and resident fish.

REQUEST for New Study: Tagging and Spawning Study of the Connecticut River Shortnose Sturgeon at the Rock Dam Pool in Turners Falls.

The USFWS’s fish passage and dam specialist John Warner reports that both downstream and upstream modifications for fish passage at Holyoke Dam will be completed this winter. New entrances and exits allowing CT River SNS to move upstream beyond that site will be working in spring 2016.

In light of the construction at Holyoke and the 2016 continuation of test flows evaluations on spring migrants in the By-Pass Reach at Turners Falls, testing of spawning success for SNS should be done at their documented natural spawning site–the Rock Dam in Turners Falls, in spring 2016. Regardless of any fine tuning needed at the Holyoke facility, some SNS will return to the Rock Dam pool by the last week of April, and the chance to study their spawning success in light of regulated test flows presents a unique opportunity for the only federally endangered migratory fish on the Connecticut River.

If this fish is ever to benefit from new genetic input, a full understanding of suitable flows at Rock Dam to accommodate spawning is necessary information going forward for a fish that has been decades on the cusp of extinction. It’s an opportunity to restore a part of the public trust.

For further information on longstanding research at this site without required test flows, see Kynard, B. and Kieffer, M.C., et al: Life History and Behaviour of Connecticut River shortnose and other sturgeons, published in 2102 by the World Sturgeon Conservation Society, ISBN 978-3-8448-2801-6.

Thank you for the opportunity to comment on the USR for these projects.

Sincerely,
Karl Meyer, M.S. Environmental Science
Greenfield, MA

Spawning shortnose sturgeon denied flow at Rock Dam Pool

Posted by on 08 May 2015 | Tagged as: 5-year FERC licensing process, American shad, Atlantic salmon, blueback herring, Connecticut River, Connecticut River ecosystem, Connecticut River shortnose sturgeon, Dr. Boyd Kynard, endangerd shortnose sturgeon, Endangered Species Act, ESA, Extinction, Federal Conte Anadromous Fish Research Center, Federal Energy Regulatory Commission, federal trust fish, federally-endangered shortnose sturgeon, FERC, GDF-Suez FirstLight, MA Division of Fish and Wildlife, National Marine Fisheries Service, Rock Dam, Rutland Herald, shortnose sturgeon, The Greenfield Recorder, University of Massachusetts, US Fish & Wildlife Service, Vermont Digger

PRockDamPoolDewatered (2)
(to view lager image, click on photo).

NOTE: the photo above documents conditions found at the Rock Dam Pool on the Connecticut River on May 3, 2015. Seventeen years of published studies conducted by federal and University of Massachusetts fisheries researchers at the adjacent Conte Anadromous Fish Research Center show that these river conditions cause spawning failure for federally-endangered Connecticut River shortnose sturgeon at the Rock Dam Pool, their only documented natural spawning site. The May 3rd river conditions found at Rock Dam mimicked mid-summer flows on the Connecticut–conditions that research shows drives spawning-ready females from the site, and de-waters the cobble-strewn pool where eggs and embryos attach and develop. April 25 to May 22 is the documented spawning window for the shortnose sturgeon on the Connecticut. It is a crime to kill, injure or interfere with endangered Connecticut River shortnose sturgeon under federal and state law. The Federal Energy Regulatory Commission, the National Marine Fisheries Service, the US Fish & Wildlife Service, and the MA Division of Fisheries & Wildlife are responsible for the protection of the Connecticut River’s only federally-endangered fish under the Endangered Species Act(ESA). GDF-Suez FirstLight controls river flows to this site via spill gate operations at the Turners Falls Dam, just upstream.

A RIVER PRESERVED IN PLASTIC Copyright © 2015 by Karl Meyer

(The following essay–with minor variation in each, appeared recently in The Recorder, The Rutland Herald, and at Vtdigger.org)

A lifeless, three-foot long Connecticut River shortnose sturgeon sits on display at the Great Falls Discovery Center in Turners Falls, MA. The shortnose has been this river’s only federally-endangered fish since 1967. That plastic sturgeon has sat amidst other replica fish for a dozen years now—a plastic American shad, a blueback herring, a trophy-size Atlantic salmon. They’re framed beneath a slightly-ruffled acrylic surface representing the Connecticut River at this flagship site of the Silvio Conte National Fish & Wildlife Refuge.

That display is the basic message offered to visitors here: ‘This is a river with congenial flows supporting populations of shad and herring, big native salmon, and federally-protected sturgeon.’

Nothing could be further from the truth.

Few upstream migrants reach Vermont and New Hampshire today. That’s part of the legacy of failure of federal and state fish agencies and watchdog groups claiming to safeguard an ecosystem and its native migratory fish. That legacy will remain intact until they confront ongoing conditions in Massachusetts that have been crippling the river here for decades.

That Discovery Center depiction falls apart if visitors simply walk outside onto the deck of the Turners Falls Bridge, adjacent to Turners Falls Dam. There, often for months on end, what they’ll see is the hollowed-out heart of New England’s Great River–a waterless chasm, or one teased by just a trickle from the power company’s dam. Conversely, when rain or snow send more river downstream than can be profitably sent through FirstLight’s power canal or stored upstream for their Northfield Mountain Pumped Storage Station, those spill gates open wide–producing violent, see-sawing flows few fish can fight or follow.

Meanwhile a 200 million year-old evolutionary gem, the Connecticut River shortnose sturgeon, remains all but abandoned just downstream–teetering on the verge of extinction for decades. Likewise, American shad can’t move upstream in the river here at all. They’re forced into that turbine-lined power canal where less than 1-in-10 will emerge alive beyond the dam. And those blueback herring–protected on paper as a “federal trust” species, have not been counted here in almost a decade. Just 20 years back they passed by the thousands.

That plastic salmon, showcased for decades as the darling of this river’s fisheries restoration, has been extinct here since 1809. It should not be presented as a living native fish. In science, extinct isn’t subject to interpretation.

That trophy-sized model derives from a massive hybrid hatchery program created by cross-breeding salmon imported from Canadian and northern New England rivers. For 43 years federal and state fish farms produced the millions of tiny fry dumped into the river each spring. Those fish factories repeatedly proved vectors for the potential spread of disease throughout the river system. Though those tiny fish proved great for public relations, no spawning population of engineered salmon ever took hold.

Hybrid salmon became the red herring that masked the massively broken ecosystem that exists on an eight-mile stretch of New England’s Great River from the Northfield Mountain Pumped Storage Station to the tailrace of the Turners Falls Power Canal. Those salmon were the stand-ins for agencies including the National Marine Fisheries Service, the USFWS, and MA Division of Fish & Wildlife that had failed to protect living migratory species here–and an ecosystem suffocating right in their backyard.

The plight of the only state- and federally endangered fish here represents the ultimate failure of responsibilities. Dr. Boyd Kynard spent decades studying the shortnose and documented it’s only natural spawning site–the Rock Dam Pool, less than two miles downstream of Turners Falls Dam. Dam operations there were annually creating conditions that crippled spawning success for the remaining 300 sturgeon still able to reach their ancient rendezvous site.

Kynard’s federal- and state-funded findings were given to fish agencies a decade back. Each bore legal responsibility for that sturgeon. Yet no agency or non-profit stepped-in to monitor and enforce Endangered Species Act protections. None intervened to halt the trickle-and-torrent flows preventing reproduction. That step alone would’ve put living waters back into the river here–aiding the shad and herring attempting to reach Vermont and New Hampshire. Likewise in 2012, when Kynard published a book on the shortnose–documenting its life history and the river conditions necessary for its recovery, again, no one went to court to protect this public legacy.

Had agencies and watchdog groups taken responsibility years back for protecting spawning sturgeon at that Rock Dam Pool below FirstLight’s dam, native migratory fish and the river ecosystem would be in a far better place today. Instead, that work was left to become part of the current studies in the Federal Energy Regulatory Commission’s 5-year relicensing process for the Turners Falls and Northfield hydro sites, where I’m on the Fisheries and Aquatic Studies Team.

Sturgeon spawning is not monitored today. It’s unconscionable to have waited for a 40 year relicensing process to come around before broaching concerns for an endangered fish and broken ecosystem. Hopefully it won’t prove the difference between a living river, and one merely depicted in a museum model.

Greenfield, MA journalist Karl Meyer is participating in the Federal Energy Regulatory Commission’s relicensing process for the Northfield Mountain and Turners Falls hydro sites.

Sturgeon spawning program at Rock Dam on Sat., April 25

Posted by on 23 Apr 2015 | Tagged as: Dr. Boyd Kynard, federally-endangered shortnose sturgeon, Rock Dam, shortnose sturgeon, Turners Falls power canal

Public invited to sturgeon spawning program in Turners Falls Saturday

Montague, MA. On Saturday, April 25, from 10:30 a.m. – 12:30 p.m. the UMass Student Fisheries Society sponsors federally-endangered Connecticut River shortnose sturgeon expert Dr. Boyd Kynard and environmental journalist Karl Meyer on a science/natural history walk to the Rock Dam in Turners Falls, the preeminent spawning site for this 200 million year old species. Kynard, who helped establish the federal Conte Fish Lab and logged 25 years as a federal researcher there, will explain the shortnose sturgeon’s life cycle and share results from three decades studying its life history and behavior. Meyer will sketch out a four-century history of the Rock Dam site, a natural, partially-inundated cliff bisecting the river, “This is a timeless place, unique both ecologically and historically in Connecticut River history” says Meyer.

Much of Adjunct UMass Professor Kynard’s shortnose sturgeon work was accomplished with the assistance of University researchers. Those collected long-term studies were published in book form in 2012, and include details on the changes required to currently-damaging hydro flows that would allow this federally-endangered species to once again successfully gather and spawn at its natural Rock Dam Pool spawning site, and begin the journey toward recovery. This public program is free, no pre-registration necessary. Meet, rain or shine, in Turners Falls, MA, at the public lot on G Street (left at first stop sign after crossing TF Canal on the 11th St. Bridge). Participants are advised to wear sturdy shoes and bring lunch if desired.

For information: 413-773-0006, and visit: www.bk-riverfish.com

New CT River Stakeholder Comments Submitted to FERC

Posted by on 14 Nov 2014 | Tagged as: American shad, By Pass Reach, Cabot Station, Connecticut River, Connecticut River Atlantic Salmon Commission, Connecticut River shortnose sturgeon, Dr. Boyd Kynard, endangerd shortnose sturgeon, Federal Energy Regulatory Commission, FERC, FirstLight, GDF-Suez FirstLight, National Marine Fisheries Service, NMFS, Northfield Mountain Pumped Storage Station, shortnose sturgeon, Turners Falls dam, Turners Falls power canal, US Fish & Wildlife Service, USFWS, Vermont

The following Stakeholder Comments/Requests on FERC Projects P-1889 and P-2485, Turners Falls Hydro and Northfield Mountain Pumped Storage were submitted on November 13, 2014 to the Secretary of the Federal Energy Regulatory Commission.

Karl Meyer, M.S. Environmental Science
85 School Street # 3
Greenfield, MA, 01301                                                              November 13, 2014

The Honorable Kimberly D. Bose, Secretary
Federal Energy Regulatory Commission
88 First Street, NE
Washington, DC 20426

ILP COMMENTS–including: Disagreements/Modifications to Study/Propose New Study on Turners Falls Hydroelectric Project P- 1889, and Northfield Mountain Pumped Storage Project P-2485.

Dear Secretary Bose,

The Turners Falls Hydroelectric Project, P-1889, and the Northfield Mountain Pumped Storage Project, P-2485, are currently undergoing studies through the 5-year FERC relicensing process in order to continue plant operations beyond 2018. An Initial Study Report Meeting Summary has been filed by GDF-Suez FirstLight. Please accept these comments on the ISR and my proposals for modifications and new study requirements in the FERC ILP for these projects.

3.3.11 Fish Assemblage Assessment:

Further information/study needed:

FirstLight has declined to undertake any study in the By Pass Reach of the Connecticut River due to stated concerns of interference with spawning and development of embryos of federally endangered shortnose sturgeon in this area. Information from the 2009 EPA study is insufficient to quantify presence and abundance of resident and migratory fish in this reach during critical migration and spawning periods—April through June. That investigation used only 3 sites in the By Pass Reach and was not undertaken to illuminate key species requirements in the current ILP for this critical reach.

NMFS notes that FirstLight has failed to consult with stakeholders on SNS issues here. I am in agreement with USFWS that a dedicated snorkeling, SCUBA, or hookah diving assessment of this critical reach of the four-state CT River be conducted in the riverbed between the Turners Falls Dam and downstream of Cabot Station during the April-June migration and spawning window–and that it continue after FirstLight’s suggested June 30 beginning target date.

I personally snorkeled parts of this reach in May 2013 and found that identification of migrants and resident species was easily attained. An in-situ investigation of this river reach in order to assess species presence and relative abundance is necessary groundwork for making decisions that will impact the 45-year long fisheries restoration on the Connecticut.

Dr. Boyd Kynard, who FirstLight cites in their argument and who spent decades investigating shortnose sturgeon on this reach of the Connecticut told me (personal communication 11/12/2014) that this study method can be accomplished without impacting SNS from the pool below the Rock Dam upstream to the base of Turners Falls Dam.

3.3.12 Evaluate Frequency and Impact of Emergency Water Control Gate Discharge Events and Bypass Flume Events on Shortnose Sturgeon Spawning and Rearing Habitat in the Tailrace and Downstream from Cabot Station.

Further information/study needed: FirstLight has supplied a grid of information for emergency gate and by pass flume openings for the years 2005 – 2012, though 2010 is missing, and we have no information on gate openings and placement for 2011 and 2012 in some instances, other than that there were no instances when greater than 4 emergency flume gates were open.

This study information should be updated with full information for years 2011, 2012—as well as 2013 and 2014 gate opening numbers, placements and CFS information.

Study findings from Kynard and Keiffer, as well as the long-term study of SNS in this reach catalogued in Life History and Behaviour of Connecticut River Shortnose and Other Sturgeons, published by the World Sturgeon Society, 2012, specifically delineate emergency and canal flume gate spill as having a profound and deleterious impact on shortnose sturgeon spawning and early life stage development.

As was stated recently by sturgeon biologist Micah Kieffer at a fall 2014 meeting of the Connecticut River Atlantic Salmon Commission, “one instance” of ramped-up or ramped-down flow from TF dam or emergency spill gate and flume operation can abruptly terminate or abort spawning attempts at Rock Dam and below Cabot Station by federally-endangered SNS for the entire year. Operations of emergency and by pass flume gates on the TF canal also can have deadly parching or burying impacts SNS embryos.

FirstLight contends that its operations of Bypass flume gates above Cabot Station are aimed at either emergency load rejection at Cabot Station, or opened to flush debris. They also contend that it is rare to have more than one flume spill gate open, though most of the numbers belie this statement–and the number of days when 4 or more gates have been open during SNS spawning window is highly significant and impactful. Opening of 4 flume gates needlessly diverts flows approaching 4,000 CFS out of the Connecticut’s By Pass Reach at TF Dam, and sends it into the canal to be needlessly flushed back into the river in a configuration that impacts migratory species and imperils annual spawning attempts of the federally-endangered CT River shortnose sturgeon.

In May 2014, I personally witnessed 3 consecutive days when two or more spill gates were open at the TF canal bypass above Cabot—all at the same time of day: 12:25 pm. These openings occurred while both Station 1 and Cabot were generating, which would appear to indicate that the spill gates had been left in this position for hours, or perhaps days, as part of flow regulation in the canal–rather than emergency or debris clearing. I have sent this information to both FERC and the federal and state fisheries agencies.

It is clear to anyone who examines the TF power canal that it is mostly a lake-like, slow-water habitat, save for the thalweg. It is rare to see debris of any significant size floating in the canal. It gets culled off at the trash racks in front of the TF Gatehouse, or at racks on the canal that dog-leg off to Station 1, or it simply settles out in the lake section of the TF Canal.

The minor amount of small, floating debris that enters the fat part of the canal is culled off by the trash rack skirt above Cabot that steers it to the east side of the canal where a bascule gate can be operated to pass anything of significant size.

The continuous openings of two or more bypass gates, up to six and seven gates open on a “non-emergency” basis on the TF canal above Cabot Station during SNS spawning and early life stage periods threatens the recovery of the Connecticut River’s only federally endangered migratory species.

As I have witnessed, multiple gates open on the canal while both Station 1 and Cabot were in operation indicates that canal flow is at times being regulated at this site, rather than at the TF Gatehouse, where excess flow could be delivered to the river in the Bypass Reach, which would nourish, rather than destroy SNS chances for successful spawning at Rock Dam and below Cabot. During SNS spawning season, mid-April – June 30th, endangered species protections dictate that all flow, save for documented, specific emergency situations, by controlled at the Head Gates of the Turners Falls Dam.

Information for years 2013 and 2014 should further be included, and a Study and study season for 2015 should be implemented that documents both the reason and instances when emergency gates were open—and any flume gates above 1 that were open to vent flow from the canal to the ByPass.

I would also like to FERC to have FirstLight include information for 2010, as the May 4 time of 8-gate emergency spill operation occurred exactly at the time frame when Northfield Mountain had burped up a massive sediment spill into its intake, and was trying to flush that pollution downstream. It would be helpful to know the position of both the Bypass flume gates and the positions of TF Dam headgates and bascule and tainter gates at that juncture—as it most definitely impacted SNS present for spawning that year. This would again offer data on whether the TF canal flows were being regulated via emergency by pass flume operation.

3.3.14 Aquatic Mapping of Turners Falls Impoundment:

Further information/study needed:

If migratory fish targeted for restoration in Northern Massachusetts and Vermont and New Hampshire are to continue to be diverted into the TF Power Canal, where few emerge upstream, then an addition to this study should be conducted: Aquatic Mapping of the Turners Falls Power Canal—as it is technically an extension of the Turners Falls Impoundment, and the public has a right to understand the habitat where their fish get privatized.

3.3.18 Impacts of the Turners Falls Canal Drawdown on Fish Migration and Aquatic Organisms

Further information/study needed:

The 2014 Canal Drawdown study was flawed as it occurred over the course of two days, due to an error in spill gate function. Since this is a study of live and dead fish and organisms, as well as the presence of dissolved oxygen, a two-day study time frame represents a flawed evaluation. A night of drying, predation, and fluctuating oxygen presence confounds the results of this work. FirstLight does an annual drawdown of the canal—has down so for decades, thus a mistake at the time of a critical habitat study should corrected by conducting a second year of study.

Further, since FERC has ordered that FL conduct a study of American shad spawning in the TF Canal, it is important to note another anomaly in their canal drawdown work. At five-year intervals the TF Canal receives a full canal muck-out during drawdown. The last one occurred in 2009. This would have been the fifth year—a time when the major muck-out would occur. It did not happen. What occurred was canal “light”, with a large snafu in the middle of the one day study, making it a two day effort. Whether FL agrees that this should have occurred in 2014 or not, a big-dig in the canal is needed regularly, as the sludge, silt and muck settles out and fills in the wide part of the basin.

This must be figured into the “impacts” of the drawdown, as it has profound implications for forcing migratory fish into this habitat, as well as the survival of resident fish and aquatics.

Please see attached photo of the canal muck-out that I took in 2009.

This is the habitat all upstream migrants are diverted into at Turner Falls

This is the habitat all upstream migrants are diverted into at Turner Falls

 

3.3.19 Evaluate the Use of an Ultrasound Array to Facilitate Upstream Movement of Migratory Fish to Turners Falls Dam by Avoiding Cabot Station Tailrace

Further information/study needed: the need for this 2016 study will be fully realized if planned studies of American shad movement and spawning in the canal confirm that these fish are experiencing significant migratory delay, and are being coralled into a migratory spawning trap by confused and insurmountable flows or pre-mature warming in artificial habitat that induces spawning in the canal—preventing fisheries restoration on the river in Northern Massachusetts, New Hampshire and Vermont.

3.3.2 Evaluate Upstream and Downstream Passage of Adult American Shad

Further information/study needed: I concur with FERC’s requirements of an intensive array of radio and telemetry receivers throughout the TF Power Canal to track migrating shad in the canal.

However, I request that FERC require FirstLight, in consultation with stakeholders, add an array temperature monitors calibrated to the radio and telemetry sites to understand whether canal delays for American shad–lingering for an average of 8 days in the TF Canal, are forcing these fish to spawn in this privatized, lake-like habitat because of warmed, shallow, and slow water conditions.

3.3.6 Impact of Project Operations on Shad Spawning, Spawning Habitat and Egg Deposition in the Area of Northfield Mountain and Turners Falls Projects

Further information/study needed:
I concur with FERC that a full spawning study of the Turners Falls Power Canal be conducted in 2015, undertaken in consultation with stakeholders. Temperature monitors should be deployed to assess impact on migratory delay and spawning on-set; and cumulative impacts of head gate and by pass use of spill gates should be factored into the study to determine the impact of silt deposits on spawning success.

3.3.9 Two-Dimensional Modeling of the Northfield Mountain Pumped Storage Project Intake/Tailrace Channel and Connecticut River Upstream and Downstream of the Intake/Tailrace

Further information/study needed: In the Initial Study Report Study Meeting Summary for stakeholder in October 2014, a request was made that FirstLight provide vector maps with arrows and indication of directional flow around the Intake and Tailrace Channel at the Northfield Mountain Pumped Storage Project. This is critical information for flow, erosion, and sediment displacement and needs inclusion.

This is information that has been missing on Northfield Mountain Pumped Storage Impacts since at least 1974. See attached at end of document.

Thank you for this opportunity to comment on these critical relicensing issues.

Sincerely,
Karl Meyer, M.S. Environmental Science
Greenfield, MA

1974 attached file below.

 

Kynard,Part II: Fisheries restoration, or a new half-century of death in the TF Power Canal?

Posted by on 06 Aug 2014 | Tagged as: American shad, By Pass Reach, Cabot Station, Connecticut River, Connecticut River ecosystem, Dead Reach, Dr. Boyd Kynard, ecosystem, Federal Energy Regulatory Commission, federal trust fish, FERC license, FirstLight, GDF-Suez FirstLight, MA Division of Fish and Wildlife, National Marine Fisheries Service, New Hampshire, Northfield Mountain Pumped Storage Station, shad, Turners Falls dam, Turners Falls power canal, US Fish & Wildlife Service, US Geological Service’s Silvio O. Conte Anadromous Fish Lab, USFWS, Vermont

Tune in to Local Bias on Greenfield Community Television, GCTV.org, for Part II of a wide ranging interview with fisheries biologist and US Fish & Wildlife Service Conte Anadromous Fish Research Center founder Dr. Boyd Kynard. He gives direct answers to questions about the fate of the millions of American shad that have been tricked out of the Connecticut River into the deadly and alien habitats of the private Turners Falls Power Canal for the last 35 years.

Dr. Boyd Kynard Part II; a Deadly Canal or a River Migration Solution?

http://mfi.re/watch/pdx5yqvqv7ygzdk/Local_Bias_147.mpg

The current Federal Energy Regulatory Commission Re-licensing process for FirstLight Power’s Turners Fall/Cabot Station and Northfield Mountain Pumped Storage Stations represents the last chance the Connecticut River gets to recover some of its biodiversity, fecundity and ecosystem functions for many decades to come. A second failure by the public agencies charged with protecting the public’s fisheries resources and endangered species will likely close off–forever, the last, best chance to restore New England’s Great River.

Will the federal and state agencies responsible for protecting and guiding the migratory fisheries restoration since 1967 (USFWS, National Marine Fisheries Service, VT, NH, and MA Division of Fish & Wildlife), again steer migratory fish headed upstream to northern MA, VT and NH spawning habitats into a private “roach motel” of deadly hydro blades and muck? Or, will they bring them directly upstream to a fish elevator at the Turners Falls and redeem decades of failure? Get the low-down, and hear about viable alternatives in this half-hour interview.

Tune in to Local Bias this Thursday, August 7 at 9 pm, or on Saturday, August 9th, at 9 pm. The shows repeat at those scheduled times the following week.

THE CONNECTICUT RIVER SHORTNOSE STURGEON: A PLANNED EXTINCTION?

Posted by on 08 Jul 2014 | Tagged as: Atlantic salmon, Connecticut River, Connecticut River shortnose sturgeon, Dr. Boyd Kynard, ecosystem, Endangered Species Act, Extinction, federally-endangered shortnose sturgeon, MA Division of Fish and Wildlife, National Marine Fisheries Service, NMFS, NOAA, Rock Dam, Turners Falls, US Fish & Wildlife Service, USFWS

Click on the link above for: Part one of Local Bias interview between Karl Meyer and Dr. Boyd Kynard, produced by Drew Hutchison of Greenfield Community Television.

Watch an interview with fisheries biologist Dr. Boyd Kynard who has made a career of researching migratory fish behavior and fish passage at dams in large rivers across four continents. Kynard is the long-standing research expert on the federally-endangered Connecticut River shortnose sturgeon.

For 45 years federal and state fisheries agencies plowed $100s-of-millions into a program targeting “restoration” of a strain of Connecticut River salmon extinct since 1809. Failing to understand the concept of extinction, that project failed.

For those same 45 years agencies including NOAA’s National Marine Fisheries Service, the US Fish & Wildlife Service, and Massachusetts and Connecticut fish and wildlife departments ignored, dismissed, and failed to provide the protections, outreach, and funding needed to rescue a native, four foot-long, living fossil: the federally-endangered Connecticut River shortnose sturgeon.

Listed among just 22 fish species in the original 1967 federal Endangered Species Act, these agencies–as well as regional non-profits, have failed to protect the 2-mile stretch of river decimated by industrial flows containing the only known natural spawning grounds of this pre- Dinosaur-Age fish: the pool below a natural rocky cleft in the river known as the Rock Dam, in Turners Falls, MA. Just 300 Connecticut River shortnose sturgeon can access the Rock Dam site today–where industrial flows cripple their spawning attempts, and endangered species protections are ignored.